FS#15158 — Nexus 3k lim1/gra1/rbx4/rbx6/sbg1/waw1
Attached to Project— Network
Planned Work | |
Whole Network | |
CLOSED | |
![]() |
Summary : We have to reload switches in the following racks to take some configuration into account
Actions : Reboot of the switches
Impact : Service will be shut during 15min per device
Start Time : 2017-11-16 02:00 (UTC)
End Time : 2017-11-16 03:00 (UTC)
Duration : 1h for all switches
List of racks concerned:
fra1-lim1-sdtor1b-n3 : L101B01
fra1-lim1-sdtor25a-n3 : L102A05
fra1-lim1-sdtor25b-n3 : L102A05
fra1-lim1-sdtor34a-n3 : L102B06
fra1-lim1-sdtor34b-n3 : L102B06
rbx6-sdtor32a-n3 : 46A04
rbx6-sdtor32b-n3 : 46A03
sbg1-sdtor4a-n3 : 61E21
sbg1-sdtor4b-n3 : 61E21
waw1-sdtor41a-n3 : W11A10
Date: Thursday, 30 November 2017, 05:31AMActions : Reboot of the switches
Impact : Service will be shut during 15min per device
Start Time : 2017-11-16 02:00 (UTC)
End Time : 2017-11-16 03:00 (UTC)
Duration : 1h for all switches
List of racks concerned:
fra1-lim1-sdtor1b-n3 : L101B01
fra1-lim1-sdtor25a-n3 : L102A05
fra1-lim1-sdtor25b-n3 : L102A05
fra1-lim1-sdtor34a-n3 : L102B06
fra1-lim1-sdtor34b-n3 : L102B06
rbx6-sdtor32a-n3 : 46A04
rbx6-sdtor32b-n3 : 46A03
sbg1-sdtor4a-n3 : 61E21
sbg1-sdtor4b-n3 : 61E21
waw1-sdtor41a-n3 : W11A10
Reason for closing: Done
Due to Black Friday and Cyber Monday period, the maintenance has been postponed to Wednesday, 29th, same hour.
Maintenance rescheduled tonight (29/11) at 02:00 (UTC)
We are starting with fra1-lim1-sdtor1b-n3
fra1-lim1-sdtor1b-n3 completed. Starting fra1-lim1-sdtor25a-n3
fra1-lim1-sdtor25a-n3 and fra1-lim1-sdtor25b-n3 completed. Starting fra1-lim1-sdtor34a-n3 and fra1-lim1-sdtor34b-n3
fra1-lim1-sdtor34a-n3 and fra1-lim1-sdtor34b-n3 completed. Starting rbx6-sdtor32a-n3 and rbx6-sdtor32b-n3
rbx6-sdtor32a-n3 and rbx6-sdtor32b-n3 completed. Starting sbg1-sdtor4a-n3, sbg1-sdtor4b-n3 and waw1-sdtor41a-n3
The switches sbg1-sdtor4a-n3, sbg1-sdtor4b-n3 and waw1-sdtor41a-n3 have been rebooted